Guide · The installation process
Fence and block wall installation, step by step
What happens between the signature and the final walkthrough — in order, with the waits called out — so you know what the contractor should be doing and when to be watching.
Published 2026-09-14. Legal references verified 2026-09-14.
As of September 2026, a fence or block wall installation in the Visalia area runs in this order: confirm the property line, handle any shared-fence notice, sign a contract that matches the quote, pull a permit where the jurisdiction requires one, notify USA North 811 at least 2 working days before digging, demolish the old structure, lay out the line, set posts or pour footings, let the concrete cure, hang panels or lay block, hang gates last, clean up, walk the line, and close out any inspection.
As of September 2026 · Visalia Fence & Wall · Get free quotes
Why the order matters
Most of the things that go wrong on a fence job go wrong because a step was skipped or done out of order: a fence built before the line was confirmed, holes dug before the utility marks were down, gates hung on posts that had not set, final payment made before the walkthrough. None of those are hard to avoid if you know the sequence. This page is the sequence, written for the homeowner rather than the crew, with the waiting steps called out so a quiet week after signing does not look like a problem.
One thing this page deliberately does not do is promise a timeline. No sourced figure for "how long a fence takes in Visalia" exists, and the real answer swings on permit review, the 811 window, cure time and the contractor's calendar. Ask for a start window and a work-day estimate in writing; then use the steps below to see where a delay is normal and where it is not.
Before the crew arrives
1. Confirm the property line
Before anything is staked, the line the fence will follow has to be agreed on. A recent survey, existing pins, or a recorded plat settles it; the contractor's tape measure from the curb does not. A fence on the neighbor's side of the line is the most expensive mistake on this list, and it is made before a single hole is dug.
2. Handle the neighbor, if the fence is shared
If the fence sits on a boundary, California Civil Code § 841 sets up a 30-day written-notice process for sharing the cost. That clock runs before the contract is signed, not after — the written quote is one of the notice's required contents. The shared-fence law page covers the five things the notice has to say.
3. Sign a contract that matches the quote
Footage, height, material, post spec, gate count, demolition, permit responsibility, 811 locate, payment terms, start window. The quote checklist covers each. If the contract is thinner than the quote, ask why. The quote checklist is the line-by-line version. And confirm the license lane one more time — C-13 Fencing Contractor for the fence, C-29 Masonry Contractor for a block or retaining wall — at cslb.ca.gov; the licensing page shows how.
4. Permit, where required
Whether the project needs a permit depends on height, placement and jurisdiction — the city building department inside Visalia, Tulare, Exeter, Porterville or Hanford city limits; Tulare or Kings County outside. Thresholds are not yet published on this site. Retaining walls are the most likely to need one, and may need engineered drawings first. This step can be the longest wait on the list.
5. The 811 locate
The contractor notifies USA North 811 at least 2 working days and not more than 14 calendar days before digging (California Government Code § 4216.2); utility owners then mark their lines with paint and flags. The ticket is good for 28 days. Do not let anyone dig before the marks are down, and do not remove the marks until the posts are in.
The two waits. Permit review and the 811 marking window are the two places a job legitimately sits still after signing. Neither is the contractor stalling. A contractor who skips either to start sooner is not doing you a favor.
On site
6. Demolition and haul-away
The old fence or wall comes out, posts and footings included — a post cut at grade with its concrete left in the ground is a shortcut that shows up when the new post needs to go in the same spot. Debris is hauled, not left in a pile for you.
7. Layout
String lines are pulled along the agreed property line, and post locations are marked at the spacing the quote specified, with corners, ends and gate posts marked separately. This is the last cheap moment to change anything.
8. Post holes, or footings
For a fence: holes are augered or dug to the depth and diameter in the contract, and posts are set — in concrete if that is what was quoted — plumb and to a line. On Visalia, Tulare and Exeter valley-floor lots the NRCS mapping shows sandy loams with hardpan in places, so the question to have asked already is what the contractor does when the auger hits hardpan. For a block wall: a trench is dug, forms and rebar are set, and a concrete footing is poured and allowed to cure before any block is laid.
9. Curing
Concrete around posts and in footings needs time before it carries load. A contractor who hangs panels the same afternoon the posts were set in wet concrete is racing the material. The wait is short, but it is a wait.
10. Rails and panels, or block courses
Fence: rails are attached, then boards, pickets or vinyl panels, working along the line with the string as reference. Wall: block is laid in courses on the footing, cells are reinforced and grouted as the plans specify, and any cap or pilaster detail is finished last. Material-specific detail — how vinyl panels lock, how wood boards are fastened, how chain link is stretched and tied — lives on the vinyl, wood and chain link pages; block detail on the block wall page.
11. Gates
Gates are hung last, after the posts have fully set, because a gate post that moves even slightly makes a gate that drags. Hardware is adjusted so the gate swings, latches and — if specified — self-closes.
Closing out
12. Cleanup and walkthrough
Excess concrete, cut-offs, packaging and dirt spoil are removed; the yard is left as it was found, less the old fence. Walk the whole line with the contractor before final payment: sight down it, push every post, swing every gate, check that the marks and flags are gone and any sprinkler lines are working.
13. Inspection, where a permit was pulled
If the job was permitted, the jurisdiction's final inspection closes it out. Final payment is commonly tied to that sign-off; the contract should say so.
Where the block wall path differs
Steps 1 through 7 are the same. From step 8 on, a wall is a different trade: a continuous footing rather than individual post holes, a cure before any block is laid, courses rather than panels, grout and reinforcement rather than rails and fasteners. It is C-29 Masonry Contractor work, and a retaining wall — one that holds back earth rather than just marking a line — is the project on this site most likely to need engineering, a permit and a final inspection. The block wall page covers footings and reinforcement; the block wall vs. wood fence page covers whether you want one at all.
What to watch, in one list
- Confirm the property line.
- Handle the neighbor, if the fence is shared.
- Sign a contract that matches the quote.
- Permit, where required.
- The 811 locate.
- Demolition and haul-away.
- Layout.
- Post holes, or footings.
- Curing.
- Rails and panels, or block courses.
- Gates.
- Cleanup and walkthrough.
- Inspection, where a permit was pulled.
Get quotes
Start at step three with the right company
Describe the fence or wall and your ZIP code. The request goes to one independent, California-licensed C-13 or C-29 company serving your address — the quote it sends is what steps one and two need.
- Cost to you: $0
- Service area: Visalia, Tulare, Exeter, Porterville, Hanford
- Who calls you: one company, named before you submit
This form does not send anywhere yet — lead routing is built in Phase 8/9 of the build plan. It is shown here to confirm layout, validation, and the section anchor the sticky bar and header quote CTAs point to.
Request fence & wall quotes
Keep reading
- Fence Installation Visalia New fences, full perimeters, gates
- Block Wall & Retaining Wall Installation Footings, reinforcement, C-29 work
- What a Quote Should Include The contract should match it line by line
- Fencing Materials Vinyl vs. wood vs. chain link
- Who Pays for a Shared Fence? Step two, in full
- How We Match Licensed Pros Verify the license before step three
Installation process questions
How long does fence installation take in Visalia?
This site does not publish a duration figure — none has been sourced, and the honest answer depends on footage, material, whether a permit is needed, and the contractor's schedule. What this page can tell you is the sequence, and which steps tend to be waits (permit, 811 marks, concrete cure) versus work days. Ask the contractor for a start window and a work-day estimate in writing.
Do I have to be home during installation?
Not usually, once the layout is agreed and access is arranged. Be there for the layout — it is the last cheap moment to change anything — and for the final walkthrough.
Who calls 811 — me or the contractor?
The person doing the excavating is the one California Government Code § 4216.2 puts the obligation on, and for a contracted job that is the contractor. It should be in the contract. If you are digging any part yourself, the requirement is yours — USA North 811 covers Tulare and Kings counties.
What if the contractor hits hardpan or something in the ground?
A good contract addresses it before it happens — either the price covers normal Visalia-area ground conditions or there is a stated per-hole charge for hard digging or obstructions. Ask. Around Visalia, Tulare and Exeter the soil mapping shows hardpan in places; this site makes no soil claim for Hanford or Porterville.
Is the process different for a block wall?
The front end is the same — line, neighbor, contract, permit, 811 — but a wall is C-29 Masonry Contractor work, not C-13 fencing, and it has a footing pour and cure before any block goes up. Retaining walls add engineering and are the project most likely to need a permit and inspection.
Can the fence be built right on the property line?
Where the fence sits relative to the line is a decision between you, the neighbor if it is shared, and local setback rules — which this site has not yet sourced for Visalia or the counties. A fence entirely inside your own line avoids the shared-fence questions altogether; a fence on the line brings § 841 into play.